| 821 |
Haryana |
PALWAL |
Bahin |
Yet to start construction |
31-07-2023 |
400 m³/day |
100 Kg/day |
100 Liters/day |
50 Kg/day |
50 Liters/day |
|
| 822 |
Punjab |
Tarn Taran |
Biogas Plant capacity 100 cubic metre with 10KW (100% Biogas genset) at Dubli dist. Tarantaran |
Functional |
30-09-2023 |
100 m³/day |
2500 Kg/day |
5000 Liters/day |
1000 Kg/day |
4000 Liters/day |
|
| 823 |
Punjab |
MANSA |
Biogas Plant capacity 100 cubic metre with 10KW (100% Biogas genset) at Khokhar Kalan dist. Mansa |
Functional |
30-09-2023 |
100 m³/day |
2500 Kg/day |
5000 Liters/day |
1000 Kg/day |
4000 Liters/day |
|
| 824 |
Punjab |
BARNALA |
Biogas Plant capacity 100 cubic metre with 10KW (100% Biogas genset) at Mannal dist. Barnala |
Functional |
30-09-2023 |
100 m³/day |
2500 Kg/day |
5000 Liters/day |
1000 Kg/day |
4000 Liters/day |
|
| 825 |
Punjab |
FAZILKA |
Biogas Plant capacity 100 cubic metre with 10KW (100% Biogas genset) at Tehna dist. Fazilka |
Functional |
30-09-2023 |
100 m³/day |
2500 Kg/day |
5000 Liters/day |
1000 Kg/day |
4000 Liters/day |
|
| 826 |
Haryana |
KURUKSHETRA |
GOBAR-DHAN Bio-Gas Plant Mathana |
Functional |
10-06-2025 |
400 m³/day |
10000 Kg/day |
20000 Liters/day |
2100 Kg/day |
0 Liters/day |
|
| 827 |
Uttar Pradesh |
BALLIA |
GP BACHAIPUR URF HASANPUR BIO GAS PLANT BALLIA |
Under Construction |
23-06-2023 |
45 m³/day |
1125 Kg/day |
350 Liters/day |
250 Kg/day |
300 Liters/day |
|
| 828 |
Punjab |
BATHINDA |
Biogas Plant capacity 100 cubic metre with 10KW (100% Biogas genset) at Harraipur dist. Bathinda |
Functional |
30-09-2023 |
100 m³/day |
2500 Kg/day |
5000 Liters/day |
1000 Kg/day |
4000 Liters/day |
|
| 829 |
Haryana |
KARNAL |
Village Hasanpur |
Under Construction |
16-01-2024 |
10 m³/day |
1000 Kg/day |
10 Liters/day |
10 Kg/day |
10 Liters/day |
|
| 830 |
Haryana |
PANIPAT |
GOBARDHAN PLANT BHODWAL MAJRI PANIPAT |
Functional |
12-01-2026 |
400 m³/day |
10000 Kg/day |
20000 Liters/day |
2100 Kg/day |
0 Liters/day |
|